We are delighted to let you know that the asphalt will be patched in a multi-phase project over the next few weeks.
While the goal is for the road to remain open during the work, there may be temporary closures or delays that impact traffic.
Here's the timeline for the work:
Monday, August 7: Asphalt cutting. No delays, half the road
will be blocked at a time.
Tuesday,
August 8 - Thursday, August 10: 2-3 days of excavation and fill work. The work will be done to half the
road at a time so vehicles may still pass. There still might be very short
delays when moving equipment or dumping rock. The plan is to do the
portions that may impact traffic first thing Tuesday morning.
Tuesday,
August 15 – ODOT will
pave starting first thing in the morning and should only take
about 4 hours. Vehicles may experience short delays.